Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
24 January 2024
December 2023 Quarterly Activities Report
Continued drilling success at Mavis Lake throughout the quarter, with strong progress also
made on permitting and technical development workstreams
Highlights
•
Resource growth drilling at Mavis Lake continued to deliver outstanding results with consistent,
thick, high-grade mineralisation. Standout new intercepts included:
- Drill-hole MF23-225 with 36.75m @ 1.12% Li2O from 208m down-hole;
- Drill-hole MF23-226 with 31.55m @ 1.06% Li2O from 205.6m down-hole, and
20.7m @ 1.44% Li2O from at 339.3m down-hole; and
- Drill-hole MF23-228 with 16.8m @ 1.18% Li2O from 177.05m down-hole, 12.85m @ 1.39% Li2O
from 208.1m down-hole and 14.85m @ 1.25% Li2O from 333.25m down-hole.
•
Drilling results confirmed that a thick mineralized pegmatite starts from surface and extends
over a strike length of 1km. Results also identified a continuous lower zone trend of high-grade
mineralisation, with assay results returning assays up to 3.53% Li2O from the lower zone.
•
Comprehensive Mobile Metal Ion (MMI) soils program and UAV-borne Magnetometry Survey
completed along with the capture of LiDAR survey and orthometric imagery around the large
spodumene-bearing outcrops in the Northern Prospects area of the Mavis Lake Project
(Gullwing and Tot). With a strike extent of more than 8km of known LCT-Type pegmatite clusters
identified, and results pending, the potential exists for a district-scale discovery.
•
Development workstreams continued to de-risk the project with dedicated efforts across
permitting, approvals and metallurgy including both waste ore sorting and direct spodumene
sorting technologies.
•
Community engagement accelerated with the Company holding its first Townhall Meeting
and the formation of a Citizens Committee to facilitate ongoing dialogue with the community
groups with an interest in and around the Mavis Lake Project area.
•
The Critical Resources Board was bolstered through the appointment of experienced lithium
and battery metals focused Geologist, Mr Nigel Broomham as a Non-Executive Director.
•
During the Quarter, the Company received a total of CAD$200,000 under the Ontario Junior
Explorer Program (OJEP) grant funding scheme.
•
The Company ended the December 2023 Quarter with $5.5m, cash fully funding work
programs for the next 9 -12 months.
Overview
Lithium exploration and project developer, Critical Resources Limited (ASX:CRR) (“Critical
Resources” or “the Company”) is pleased to report on its activities for the quarter ended
31 December 2023 (“the Quarter”).
Critical Resources Limited
ABN 12 145 184 667
ASX:CRR
Level 45. 108 St Georges Terrace, Perth WA 6000
P. +61 9468 1024 W. criticalresources.com.au E. info@criticalresources.com.au
During the Quarter, the Company remained firmly focused on delivering on its strategy of resource
growth in parallel with project development at its flagship asset in Canada, the Mavis Lake Lithium
Project (“Mavis Lake”).
The continued development of Mavis Lake comes at a time when the North American battery
minerals and electric vehicle sectors are growing rapidly, with unprecedented investment by
major vehicle and battery manufacturers along with strong policy and financial support from
United States and Canadian policymakers.
Operational Activities
Mavis Lake Lithium Project (100%) – Ontario, Canada
Active exploration drilling targeting resource growth continued during the Quarter. Assay results
released throughout the Quarter confirmed the presence of continuous, thick, high-grade
mineralisation starting from surface and extending over 1 kilometre in strike (Figures 1 and 2).
Consistent with the Company’s dual-track strategy, project development workstreams continued
with a focus on environmental data collection, permitting, environmental studies, metallurgical
test work, mining studies and project economic analysis. On-the-ground community consultation
also continued in lockstep with technical project works.
Main Zone Exploration. Drilling continued through the Quarter with a focus on resource growth
within the Main Zone. Assays reported during the Quarter confirmed and extended the recently
discovered Swell Zone. When integrated with previous drilling results, they show a thick, high-grade
mineralised structure, starting from surface and extending over 1km in strike length and sitting
oblique to the current Mineral Resource Estimate (MRE).
After incorporating historical drilling, the Company has now achieved tight drill spacing
(approximately 50m spacing) across the deposit. Much of the Swell Zone mineralisation sits outside
the current MRE for Mavis Lake and presents an immediate opportunity for Resource growth.
Figure 1 – Mavis Lake Main Zone plan view
Page 2 of 10
Figure 2 – Mavis Lake Main Zone Long Section
Table 1 – Significant Assay Results for the Quarter
Hole ID
From (m)
To (m)
Down Hole Interval (m)
Li2O (%)
True Width (m)
MF23-217
including
212.1
223
251.65
251
39.55
28
0.86
1.01
23.7
16.8
MF23-221
including
161.6
161.6
179.3
172.3
17.7
10.7
0.79
1.24
11.5
7.0
MF23-222
including
236.25
247.5
266.75
265.4
30.5
17.9
0.78
1.09
18.3
10.7
MF23-225
including
and
208
209.8
347.2
244.75
243.3
354.9
36.75
33.5
7.7
1.12
1.21
1.3
23.9
21.8
6.9
MF23-226
and
and
145.7
205.6
339.3
155.65
237.15
360
9.95
31.55
20.7
1.24
1.06
1.44
7.5
23.7
18.6
MF23-228
177.05
193.85
16.8
1.18
12.6
and
and
and
208.1
290.15
333.35
220.95
293.45
348.2
12.85
3.3
14.85
1.39
1.12
1.25
9.6
2.5
13.4
MF23-229
and
and
and
124.55
202.4
353.4
375.5
134.3
207.8
362.07
382.06
9.75
5.4
8.67
6.56
1.06
1.02
1.13
1.21
7.3
4.1
7.8
5.9
As well as extending the primary mineralised structures of the Main Zone, the drilling completed in
the Quarter consistently intersected a lower zone, which comprises thick, high-grade mineralisation
Page 3 of 10
as seen in Figure 3 with drill-hole MF23-226 returning 20.7m @ 1.44% Li2O. The entirety of the lower
zone sits outside the current MRE, and its discovery has the potential to add both tonnage and
grade to Mavis Lake deposit.
This newly discovered pegmatite represents an enticing exploration target, with promising
opportunities explore its trend and connections with neighbouring pegmatites.
Figure 3 – Cross-section highlighting MF23-226’s Main Zone and Lower Zone intercepts
The 2023 drilling program concluded in mid-November, with final assay data still outstanding. The
pending results, along with target generation work at the Northern Prospects, will be used to inform
and prioritise exploration plans for 2024.
Page 4 of 10
Northern Prospects target development. Work at the Northern Prospects during the quarter
continued to demonstrate the district-scale potential of Mavis Lake. Various exploration
techniques were utilised, focused on and around the large spodumene-bearing outcrops within
the Northern Prospects area.
Pegmatites at the Gullwing-Tot Prospects are located within an E-NE trending cluster that extends
over an approximate area of 0.8-2.2 km by 8 km. Geological mapping, litho-geochemical Mobile
Metal Ion (MMI) soil sampling, as well as LiDAR and airborne-magnetometry surveys were
undertaken to develop and refine drill targets.
Target areas for geophysics and soil sampling programs completed during the Quarter are shown
in Figure 4. Assay results are expected over the coming months. Data analysis, integration and
interpolation will be completed as results are received. The ability to layer multiple datasets will be
instrumental in developing high-confidence drill targets.
Figure 4 – Soil sample points and UAV Magnetometry flight area.
The Company received drill permits for the Northern Prospects in late December 2023. Once the
field work results from the Quarter are received, the Company expects to develop an initial drilling
program for the Northern Prospects as part of its 2024 exploration program.
QA/QC and umpire testing. During October and November, Critical Resources initiated an Umpire
Lab Sampling Test program to independently assess the Company’s primary independent
laboratory completing assays on the Mavis Lake Project. This annual process was completed as
Page 5 of 10
part of Critical Resources internal QA/QC processes, with AGAT Laboratory in Thunder Bay, Ontario
selected as the Umpire Laboratory.
A batch of samples, comprising over 5% of Critical Resource's Mavis Lake assays, was prepared
and sent to AGAT Laboratory in October, with analysis and reporting completed in November. The
Umpire Lab results exhibited an average variance of 0.008% Li2O. The standard samples fell within
ranges below 3 standard deviations of the expected control assay results provided. Blank samples
returned results below the detection limit, indicating precision success in the testing process.
Metallurgical Testwork. During the Quarter, Saskatchewan Research Council (SRC) and STARK
Resources were contracted to conduct a collaborative testwork program to assess the
amenability of Mavis Lake ore to beneficiation by coarse, dry ore sorting.
A drill core sample suite, encompassing the full range of ore and rock types exhibited at Mavis
Lake, was prepared and dispatched for testwork. Mineralogical assessment of the rock and ore
types will be completed first, followed by X-ray Transmission (XRT) based amenability studies to
assess the viability of pre-concentrating mined ore by rejecting coarse waste rock.
Samples of ore will also be subjected to an ultra-violet (UV) laser-based amenability study with
STARK’s technology partner, Optimum Sorting. This innovative technology detects spodumene
directly and offers unique opportunities in the production of spodumene concentrate by
separating spodumene from the unmineralised host pegmatite.
The removal of mined waste rock and gangue minerals in the coarse, dry beneficiation stage offers
tangible operational benefits including increased mineable tonnes, reduced haulage, lower
energy and water consumption and associated emissions, reduced grinding and milling capacity
requirements, improved feed grade consistency and plant productivity and reduced tailings. The
testwork program commenced in December 2023. Initial results are expected in Q1 2024.
Baseline Studies. The Quarter saw the continuation of field-based environmental baseline studies
and data capture, which are essential activities that sit on the project’s critical path. Key
workstreams undertaken during the Quarter were:
•
•
•
•
•
•
•
Surface water quality and hydrology data capture;
Stage 1 archaeology studies including consultation and input from First Nations Communities
(completed for both the Mavis Lake area as well as the Gullwing and Tot areas);
Ecological classification of vegetation communities;
Studies of breeding birds and an evaluation of potentially significant wildlife habitat;
Trail cameras were deployed in November to capture the fall wildlife activities;
Geochemistry assessment was initiated, with results due in 2024 – results to be used to support
mine planning and waste rock management assessments;
Initial hydrogeology study (groundwater) was commenced to establish baseline conditions
and allow for trend assessment of groundwater conditions. The outcomes of hydrogeology
studies will inform both mine planning and process water requirements.
Graphic Lake Lithium Project (100%) – Ontario, Canada
No exploration activities were completed during the Quarter.
Page 6 of 10
Plaid and Whiteloon Lake Projects (100%) – Ontario, Canada
No exploration activities were completed during the Quarter, desk-top analysis identified little to
no prospectivity for lithium, the Company has deemed these claims as non-core, the claims are
expected to lapse in the following quarter.
Halls Peak Project – New South Wales, Australia
No exploration activities were completed during the Quarter. During the Quarter, the Company
received $68,500 from the NSW Government, along with the release of a $95,000 bank guarantee,
both of which related to security deposits held against exploration permits for EL4474. The security
was released following the approval of rehabilitation activities completed during the second half
of 2023.
Sohar Block 4 and 5 Project – Sultanate of Oman
No exploration activities were completed during the Quarter. The Company has deemed the
Sohar Project as non-core and is evaluating divestment opportunities.
Schedule of mineral tenements
The Company’s tenement and claim schedule is provided in Appendix 1.
Lithium Market and Industry
In November, the Government of Canada launched a CAD1.5 billion Critical Minerals
Infrastructure Fund (CMIF) to support critical minerals development. The fund will finance essential
common-use infrastructure such as roads, rail, transmission lines and ports to unlock remote critical
mineral deposits. The Company is assessing opportunities to access Canadian government
funding in collaboration with a range of potential partners within Ontario and Internationally.
During the Quarter, the US Government also released rules that provide full tax credits for electric
vehicles with locally-sourced battery materials and components. Vehicles containing raw
materials such as lithium and nickel supplied by a foreign entity of concern (FEOC) will not
necessarily qualify for the tax credit. Suppliers from countries such as Canada and Australia who
can demonstrate they are not controlled by a FEOC will not be impacted.
During the Quarter Exxon, the largest US oil company, announced intentions to move into the
lithium industry, with plans to become a leading supplier to the industry by 2030.
In late December, S&P Platts reported minimal buying activity on the spot market, the Company
notes that low volume buying currently seen is seasonally the norm at the end of the calendar year
and leading into the Chinese New Year.
Recent announcements by operating lithium companies advising on reduction/cessation of
production provide an indication that current pricing is likely to be at unsustainably low levels.
Platts has reported similar views, with non-integrated refineries in China assessed to be operating
at a loss.
Page 7 of 10
Communities and Sustainability
During the Quarter the Company continued its regular engagement with First Nations Communities
and also initiated formal dialogue with broader residential communities in and around Dryden.
A Public Townhall Meeting was held in October with members of the Critical Resources Board and
management team providing updates on the Company’s activities over the past 18 months and
also plans for the future, followed by an open Q&A session. The Company was grateful for the over
150+ people who took the time to attend the Townhall Meeting and the spirit in which the evening
was conducted.
During the Townhall Meeting, Critical Resources made a commitment to provide a formal
mechanism to inform and update the interested parties in and around the project area. A Citizens
Committee has subsequently been formed with Terms of Reference agreed. The Citizens
Committee will meet quarterly and is an initiative to ensure open and transparent dialogue
between Critical Resources and the community.
Finance
Exploration Expenditure. The Company invested approximately AUD$1.3m in exploration activities
across its project portfolio during the Quarter, approximately 97% was focused on Mavis Lake, with
almost all Mavis Lake expenditure allocated to drilling, field geological support assays and
exploration consumables.
Grant funding. During the Quarter, the Company received a total of CAD$200k (AU$226k) under
the Ontario Junior Explorer Program (OJEP) grant funding scheme. The funding grant was directly
allocated against exploration work within the Mavis Lake Project Area.
Cash Position. The Company held cash and cash equivalents of AUD$5.5m as at 31 December
2023.
Other Disclosure. As disclosed under item 6 in the Appendix 5B, the Company made payments to
related parties for a total consideration of AUD$111k. This consideration relates to payments
attributable to routine Director fees, salaries and statutory superannuation.
Corporate Activity
Board Appointment. During the Quarter, Critical Resources appointed senior Geologist and highly
experienced lithium professional, Nigel Broomham, as a Non-Executive Director.
Mr Broomham has more than 12 years of industry experience, principally in hard rock lithium
exploration, resource development and operations.
Change of Corporate Address. During the Quarter, the Company advised of a change in
registered office and principal place of business: Level 45, 108 St Georges Terrace, Perth WA 6000.
All other contact details remain unchanged.
Page 8 of 10
Key Announcements during the Quarter
During the Quarter, the following key announcements were released:
12 December 2023
Project Development Activities Continue on Multiple Fronts to Advance
Mavis Lake Lithium Project
28 November 2023
Mavis Lake Beneficiation and Optimisation Studies to be Bolster by Ore
Sorting Test Work
15 November 2023
Assay Results Extend Swell Zone at Mavis Lake – Starting from Surface and
Extending over 1km in Strike
2 November 2023
District-Scale Potential at Mavis Lake Norther Prospects with Multiple Drill
Targets
19 October 2023
Further Outstanding Assays Extend the Mavis Lake Swell Zone
9 October 2023
Experienced, Lithium-Focused Geologist Joins the Board to Support Resource
Growth at Mavis Lake
This announcement has been approved for release by the Board of Directors.
-endsFor further information please contact
Alex Cheeseman
Managing Director
E: info@criticalresources.com.au
P: +61 (8) 9468 1024
Nicholas Read
Read Corporate
E: nicholas@readcorporate.com.au
M: +61(0)419 929 046
ABOUT CRITICAL RESOURCES LIMITED Critical Resources is focused on the exploration, development and delivery of the
critical metals required for a decarbonized future, underpinned by a portfolio of lithium projects in Ontario, Canada
which are ideally positioned to participate in the rapidly growing North American battery materials supply chain. The
Company’s principal focus is on its flagship Mavis Lake Lithium Project in Ontario, Canada, where it has completed
over 45,000m of drilling and defined a maiden Inferred Mineral Resource of 8Mt grading 1.07% Li2O. Recent exploration
success has demonstrated substantial potential to expand this resource and make new discoveries in the surrounding
area. Critical is progressing a dual-track strategy at Mavis Lake of targeting resource growth in parallel with multiple
permitting and project development workstreams.
COMPLIANCE STATEMENT This document contains information on the Mavis Lake Lithium Project extracted from ASX
market announcements dated 25 October 2021, 16 June 2022, 21 July 2022, 1 September 2022, 13 September 2022, 24
October 2022, 27 March 2023, 27 June 2023, 24 July 2023, 21 August 2023, 19 September 2023, 19 October 2023, and
15 November 2023, reported in accordance with the 2012 edition of the “Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves” (2012 JORC Code) and available for viewing at
https://www.criticalresources.com.au/. The Company confirms that it is not aware of any new information or data that
materially affects the information included in any original ASX market announcement.
FORWARD LOOKING STATEMENTS This announcement may contain certain forward-looking statements and projections.
Such forward looking statements/projections are estimates for discussion purposes only and should not be relied upon.
Forward looking statements/projections are inherently uncertain and may therefore differ materially from results
ultimately achieved. Critical Resources Limited does not make any representations and provides no warranties
concerning the accuracy of the projections and disclaims any obligation to update or revise any forward-looking
statements/projects based on new information, future events or otherwise except to the extent required by applicable
laws. While the information contained in this report has been prepared in good faith, neither Critical Resources Limited
or any of its directors, officers, agents, employees or advisors give any representation or warranty, express or implied, as
to the fairness, accuracy, completeness or correctness of the information, opinions and conclusions contained in this
announcement.
Page 9 of 10
Appendix 1 – Schedule of mineral tenements at 31 December 2023
Claim Number
Project /
Location
Disposed
interest
during
quarter
Interest at
end of
Quarter
101034, 101215-101218, 101616-101619, 103512, 107330107331, 109871, 110434, 110703, 116376, 117689-117690,
123068, 124332, 129509, 130111, 130299-130330, 135026,
135728, 138331, 138446, 139468-139470, 141103, 141801,
143041, 143046-143047, 144330, 144441, 151583-151585,
151642,157160-157161, 158448, 158546, 160902, 166897,
167079-167080, 167677, 168187-168188, 168229, 168328168329, 176105, 176198, 179416-179418, 179741-179743,
180192, 108489, 181000, 181037, 182187, 186194, 187649,
188359, 189624, 190960-190961, 196153-196154, 197591,
198244-198246, 199857, 201802, 203140-203142, 203594,
203763, 205589, 205676, 207864, 209134-209136, 210239,
210439, 212294-212295, 215413, 215824, 216365-216366,
228777-228778, 230161-230162, 233613-233614, 233867,
234948, 235582, 239067, 240149, 246549, 247620, 253509253510, 254970, 256451-256452, 256960, 257849, 257852,
259169, 259285, 264260, 266452, 267141, 270261, 271534,
271591, 272225-272226, 273079, 274526, 275823-275825,
278758, 281841, 282015, 283653-283655, 284320-284321,
286761-286763, 289910, 290059-290060, 290972, 292149,
302230, 303032, 303733-303734, 305020-305022, 306990,
307466-307467, 310379-313380, 312334, 314170-314171,
316293-316294, 316884, 325843, 326459, 329628-329631,
703383-703516, LEQ-108830 – LEA-108835, 76580-765816,
766092-766191, 766195-766294, 766540-766589, 766636766685, 766745-766794, 766848-766898
Acquired
Interest
during
quarter
Mavis Lake
Ontario
Canada
-
-
100%
-
-
100%
-
-
100%
-
-
100%
-
-
59.5%
-
-
65%
710276-710332, 710441-710491, 710659-710826, 710995711044, 717564-717591
659224-659228, 659230-659241, 686985 – 686998, 702287702311, 702357-702389,
EL 4474, EL 9428 – EL9430
EL 7679
Block 5*
Plaid &
Whiteloon
Lake
Ontario
Canada
Graphic Lake
Ontario
Canada
Halls Peak
NSW
Australia
Halls Peak
NSW
Australia
Oman
Block 4*
Oman
51%
* It is noted that in accordance with their terms and conditions, the Company has submitted the required annual extension
applications with respect to the Oman exploration licences and is awaiting confirmation if its application has been
accepted. This does not apply to the Oman mining licences.
Page 10 of 10
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Critical Resources Limited
ABN
Quarter ended (“current quarter”)
12 145 184 667
31 December 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date (12
months)
$A’000
-
-
(a) exploration & evaluation
-
-
(b) development
-
-
(c) production
-
-
(d) staff costs
(198)
(744)
(e) administration and corporate costs
(450)
(1,463)
-
-
41
59
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
226
226
1.8
Other (provide details if material)
69
69
1.9
Net cash from / (used in) operating
activities
(312)
(1,853)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(1)
(15)
(1,256)
(8,841)
(e) investments
-
(2,149)
(f)
-
-
(c) property, plant and equipment
(d) exploration & evaluation
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date (12
months)
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
(1,257)
(11,005)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
10,166
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
177
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
(530)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
(16)
(27)
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (Repayment of lease liabilities)
(45)
(85)
3.10
Net cash from / (used in) financing
activities
(61)
9,701
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
7,273
8,573
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(312)
(1,853)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(1,257)
(11,005)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
(61)
9,701
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date (12
months)
$A’000
4.5
Effect of movement in exchange rates on
cash held
(148)
79
4.6
Cash and cash equivalents at end of
period
5,495
5,495
5.
Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
5.2
Current quarter
$A’000
Previous quarter
$A’000
5,176
6,942
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (security deposits)
319
331
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
5,495
7,273
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
1111
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
0
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
1 Related party
payments are attributable to director fees and salaries.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
-
Not applicable
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(1,256)
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(1,568)
8.4
Cash and cash equivalents at quarter end (item 4.6)
5,495
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
(312)
5,495
3.5
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accoun