Maiden Mineral Resource Estimate for the Halls Peak Project
Released
Released
Announcement PDF
ASX Announcement
30 June 2023
Maiden Mineral Resource Estimate for the Halls Peak
Zn-Pb-Cu-Ag-Au Project
Highlights
•
Maiden JORC 2012 Compliant Mineral Resource Estimate (MRE) completed for the Halls
Peak Project in NSW following a series of successful drilling programs comprising 47
diamond core drill holes over four separate drilling campaigns, for a total of 6,921 metres.
•
The drilling programs have confirmed the presence of multiple stacked lodes of both
base metal (zinc, lead, copper) and precious metal (silver, gold) mineralisation.
•
The drilling has also expanded the scale of known mineralization (both laterally and
vertically), confirming large-scale potential of the Halls Peak System.
•
The Inferred Mineral Resource contains 840,000 tonnes @ 3.7% zinc, 1.5% lead, 0.44%
copper, 30 grams/tonne silver and 0.1 grams/tonne of gold at a 2.0% zinc cut-off grade.
•
Mineralisation remains open along strike, and at depth, offering the potential to increase
the MRE through follow-up drilling.
Lithium development company Critical Resources Limited ASX:CRR (“Critical Resources” or “the
Company”) is pleased to announce a maiden JORC Code 2012 compliant Mineral Resource
Estimate (MRE) for its 100%-owned Halls Peak Base Metals Project, in New South Wales, Australia.
Halls Peak is a base and precious metal asset which formed part of Critical’s mineral portfolio
before its acquisition of the flagship Mavis Lake Lithium Project in Ontario, Canada.
Resource Overview
A maiden Inferred Mineral Resource of 840,000t grading 3.7% zinc, 1.5% lead, 0.4% copper, 30ppm
silver and 0.1ppm gold has been estimated following recent drilling campaigns.
Modelling has shown that the mineralisation remains open along strike to the east/north-east and
west/south-west, providing immediate potential to increase the MRE with follow-up drilling.
An Exploration Target has been prepared in accordance with the JORC Code (2012).
The Exploration Target of 500,000 to 1,000,000 tonnes at similar grades to the current Maiden MRE
(2.7-3.7% zinc, 1.1-1.5% lead, 0.34-0.44% copper, 27-33ppm silver and 0.08-0.12ppm gold) has been
defined based on modelling and interpretation of the current Resource.
The potential quantity and grade of the Exploration Target is conceptual in nature, there is currently
insufficient exploration completed to estimate a mineral resource of this size, and it is uncertain
whether further exploration will result in the estimation of an increased JORC Mineral Resource.
Critical Resources Limited
ABN 12 145 184 667
ASX:CRR
Level 50. 108 St Georges Terrace, Perth WA 6000
P. +61 9389 4499 W. criticalresources.com.au E. info@criticalresources.com.au
Requirements for Material Mining Projects
The following subheadings are provided to satisfy the requirements applicable to reports of Mineral
Resources for material mining projects under ASX Listing Rule 5.8.
Geology and Geological Interpretation
The Halls Peak Project (Exploration License (EL) 4474) is located approximately 45km south-east of
Armidale, New South Wales in the New England Fold Belt, an area well known for its mineral
endowment and historical production. Halls Peak hosts a large polymetallic mineral system. Drilling
campaigns within EL4474 have confirmed multiple stacked lodes of base (Zinc, Lead and Copper)
and precious metals (Silver and Gold) mineralisation.
The Halls Peak massive sulphide deposits were discovered in 1896 where near surface mining
extracted high-grade zinc, lead, copper and silver. Recent exploration drilling has yielded excellent,
high-grade intersections of zinc, lead, copper and silver. Multiple geological and geophysical
targets exist across the Halls Project which along with the resource modelling that underpins the
MRE, form the basis for further exploration and growth of the known resource.
Halls Peak is considered to have potential to contain world class deposits similar to those already
being mined in northern Australia. The project area comprises multiple historic mines and prospects
including Gibsons, Sunnyside, Firefly, Faints, Khans Creek, Keys and Mickey Mouse.
All exploration activities completed by the Company are focused on EL4474 with primary effort
around the Gibsons prospect where the Mineral Resource has been defined.
The vast majority of the lateral and vertical extent of the system has never been drill tested. SEDEX
Zinc-Lead-Copper-Silver deposits are interpreted by the Company to be the dominant
mineralisation style discovered at Halls Peak.
Sampling and Sub-Sampling Techniques
Refer to details provided in Appendix 1, JORC 2012 Table 1, Section 1: Sampling Techniques
Summary statistics for composites within the mineralised zone are presented in Table 1. All elements
show moderate coefficients of variation (CV = SD/mean) indicating that there are some extreme
values, indicated by the maximum grades, requiring special treatment during grade estimation.
Ordinary Kriging (“OK”) with grade cutting was utilised to deal with extreme values as an
appropriate estimation method because of the moderate coefficients of variation.
Table 1: Summary of Composite Statistics for Mineralised Zone
Element
Samples
Zn %
Pb %
Cu %
Ag ppm
Au ppm
3,830
3,830
3,830
3,830
3,830
Min
Max
Mean
SD
CV
0.005
0.0002
0.0004
0.07
0.0005
49.2
22.6
6.94
2,385
4.42
1.345
0.614
0.202
20.9
0.066
4.067
2.147
0.608
98.1
0.192
3.02
3.50
3.00
4.70
2.91
Figure 1 is a histogram of zinc, which is typical of composite grades within the mineralised zone,
showing multiple overlapping grade populations and a large spike (18% frequency) at 0.01%
representing the inserted low default values.
Page 2 of 25
Figure 1: Histogram of Zinc Grades for Mineralised Zone
Density
Density values were derived from 50 samples with density measurements from five recent drill holes.
Analysis was performed by ALS Method OA-GRA08, described as “Specific Gravity on solid object”.
This method determines specific gravity, rather than bulk density, by weighing a sample in air and
in water, without wax coating.
Dry bulk density is the attribute required for resource estimation, but it is unclear if the method used
here is significantly different. Samples were dried at 105°C in an oven for 7 hour 30 minutes, with a
nominal sample size of 10cm long portions of quarter core. Measurement frequency is 10 samples
per hole on average, which is equivalent to around one sample per 15m drilled. Density data was
merged with assays for further analysis. The proportions of galena, sphalerite and chalcopyrite were
calculated from Pb, Zn and Cu assays respectively and used to calculate a density value for each
sample with a gangue density of 2.70. Summary data can be seen in Table 2
Table 2: Summary of Halls Peak Density Data
Item
Count
Min
Max
Mean
Median
SD
All Samples
Trimmed
SG_Calc2
50
48
50
2.34
2.59
2.70
4.26
4.26
4.41
2.95
2.97
2.95
2.82
2.83
2.81
0.42
0.41
0.36
Drilling Techniques
Refer to details provided in Appendix 1, JORC 2012 Table 1, Section 1: Drilling Technique, Drill
Sample Recovery and Sampling Techniques
Resource Database
Table 3 shows a database summary of the relevant holes used in the MRE. All holes were drilled as
diamond core and the Company drilling represents 47% of holes and 69% of total meterage. The
All State NL holes were drilled in 1969 and 1970, while the Company holes were drilled in 2021 and
2022. Precious Metal Resources Limited (ASX:PMR) held the property between 2011 and 2014, and
Sovereign Gold Company Limited (ASX:SOC) explored the property from 2014 until acquired by
the Company.
Page 3 of 25
The database also included nine tunnels represented as drill holes, however there was no
geological logging or assays for these workings in the digital database.
Table 3: Resource Database Summary
Item
Collar
Survey
Assay
Geology
All State NL
Precious Metal
Sovereign Gold Critical Resources
Total
Holes Records Holes Records Holes Records Holes Records Holes Records
14 1,120m
14
28
14
432
14
331
5
5
5
4
382m
10
275
188
6
6
6
6
637m
12
366
324
22 4,782m
22
157
22
2,090
22
1,970
47 6,921m
47
207
47
3,163
46
2,813
Cu
Pb
Zn
Au
Ag
Fe
S
As
Sb
14
14
14
14
14
0
0
0
0
432
432
432
432
432
0
0
0
0
5
5
5
5
5
0
0
0
0
273
273
273
273
273
0
0
0
0
6
6
6
6
6
0
0
0
0
365
365
365
365
365
0
0
0
0
22
22
22
22
22
22
22
22
22
1,848
1,848
1,848
1,748
1,848
1,848
1,848
1,848
1,848
47
47
47
47
47
22
22
22
22
2,918
2,918
2,918
2,818
2,918
1,848
1,848
1,848
1,848
Lith
CoreRec
Density
14
14
0
340
338
0
4
4
0
189
192
0
6
2
0
331
121
0
22
22
5
2,302
2,312
50
46
42
5
3,162
2,963
50
Sample Analysis Method
Covered in detail in Appendix 1, JORC 2012 Table 1, Section 1: Sampling Techniques, Sub-sampling
Techniques and Sample Preparation, Quality of Assay Data and Laboratory Tests and Verification
of Sampling and Assaying
Mining and Metallurgy
Surface mining by open pit method is currently assumed for Halls Peak.
It is assumed that sulphide ore will be treated by conventional froth flotation to produce a bulk ZnPb-Cu sulphide concentrate. Gold may also be recovered by gravity concentration.
No metallurgical testwork has been undertaken in support of the MRE. Peer comparison values have
been used to support the concept of economic extraction.
Estimation Methodology
The Resource Estimate was developed from the generation of a rotated block model, with blocks
dipping 55°>330°, which is the general orientation of the higher-grade mineralisation in the central
part of the deposit.
This orientation ensures optimal estimates for the best drilled section of the deposit. Table 4 gives
the model extent and block size in MGA94 Zone 56 grid coordinates.
Table 4: 2023 Halls Peak Model Dimensions
MGA94 Zone 56
Origin
Maximum
X
407,400
407,800
Y
6,598,000
6,598,400
Z
400
1,000
Page 4 of 25
5
80
400
Block Size
Number of blocks
Length
2
200
400
5
120
600
The small block size was chosen due to hole spacing in some areas being 10m or less, so a 5m
block is justified in these areas, and in areas where the orientation of mineralisation is significantly
different to 55°>330°, a small block size is required to give reasonable resolution. The 2m block
dimension in Y reflects the shorter continuity perpendicular to the plane of mineralisation.
Blocks were trimmed to topography and within a boundary between 500-900m in Z (elevation)
and 6,597,750-6,598,250m in Y (Northing).
Metal grades were estimated using OK with soft boundaries between the mineralisation and
surrounding material. A dynamic search was implemented using the boundaries of the broad
envelope of mineralisation defined by assays to assign dip and dip direction to each block. A
three-pass search strategy was used, as outlined in Table 5, and estimates were discretised over
5x5x2 points within each block.
Table 5: Estimation Search Parameters
Pass
1
2
3
X
Search Radii
Y
Z
15
30
60
3
3
3
15
30
60
Min
Samples
Max
Min Oct
8
8
8
24
24
24
4
4
4
The minimum number of samples and octants (Min Oct) ensure that blocks are estimated by a
minimum of two holes and avoids excessive extrapolation of grades.
A progressive grade cutting strategy was employed to limit the influence of extreme values, with
the first pass top-cut to the 99th percentile of each grade distribution, pass 2 to the 98th percentile
and pass 3 to the 95th percentile. Table 6 gives top-cut grades used for each estimation pass.
Table 6: Progressive Grade Top-cuts
Percentile
Zn %
Pb %
Cu %
Ag ppm
Au ppm
99
98
95
24
18
7.35
14
8.5
3.2
3.5
2.5
1.27
360
235
75
0.69
0.44
0.24
Dry bulk density was assigned to the model using a formula based on estimated base metal
grades. There is no allowance for potentially lower densities in weathered/oxidised rock.
Model Validation
The model was validated in a number of ways – visual comparison of block and drill hole grades,
statistical analysis and examination of grade-tonnage data.
Visual comparison of block and drill hole grades showed good agreement in all areas examined
and minimal evidence of excessive smearing of high grade assays. A few examples are presented
in Figure 2 and Figure 3, which show the strike and dip of mineralisation respectively.
Page 5 of 25
The majority of blocks (62%) were estimates in pass 3, which used samples cut to the 95th percentile.
Comparing average cut sample grades to the average block grades comparison can be seen in
Table 7, and differences can mostly be attributed to sample clustering.
Figure 2: Plan @ 750mRL with 50m clipping
Figure 3: Section on DDHA2, azimuth 330 & 20m clipping
Page 6 of 25
Table 7: Sample and Block Grade Comparison – Mineralised Zone (cut to 95th percentile)
Element
Samples (Cut)
Number
Mean
Blocks
Number
Mean
Zn %
Pb %
Cu %
Ag ppm
Au ppm
3,830
3,830
3,830
3,830
3,830
73,587
73,587
73,587
73,587
73,587
0.882
0.347
0.143
9.91
0.048
0.684
0.273
0.108
8.23
0.037
Blk/Sam
Mean
78%
79%
75%
83%
78%
Figure 4 presents a grade-tonnage curve for the entire model at a range of zinc cut-off grades
and shows a smooth and logical transition from one cut-off grade to the next, with no obviously
anomalous kinks or plateaus that might be indicative of estimation problems, such as conditional
bias.
Figure 4: Grade-Tonnage Curve for Halls Peak
Cut-off Grade
A notional equivalent metal value has been derived to aid interpretation and to also assess the
value contribution of each metal. Current nominal metal prices and metallurgical recoveries of
85% for all metals were assumed, and grade-tonnage analysis of the model on this basis showed
that zinc was the major contributor of value, with almost half (~47%) of total metal value.
Consequently, the model was evaluated using a zinc cut-off grade.
The cut-off grade of 2.0% Zn is considered potentially economic for open-pit mining and is
comparable to cut-off grades used by peer companies with similar deposits.
Mineral Resource Estimate
The MRE has been reported in accordance with The JORC Code 2012.
The MRE has been trimmed to blocks within 100m of surface to generate the MRE and account for
the JORC concept of “reasonable prospects for eventual economic extraction”. It is assumed that
the MRE would be extracted by open-pit mining.
The MRE has been classified in accordance with guidelines contained in the JORC Code. Key
criteria that have been considered when classifying the Mineral Resource are detailed in JORC
Table 1.
Page 7 of 25
This classification is based upon assessment and understanding of the deposit style, geological and
grade continuity, drillhole spacing, input data quality (including drill collar surveys and bulk density).
The Mineral Resource was classified as Inferred, accounting for the level of geological
understanding of the deposit, quality of samples, density data, drillhole spacing and sampling,
analytical and metallurgical processes. Material classified as Inferred was considered sufficiently
informed by geological and sampling data to imply geological, grade and quality continuity
between data points.
The classification reflects the level of data available for the estimate, including input drillhole data
spacing, and high level of confidence in geological continuity for this particular style of deposit.
Mineral Resources are reported at a nominal 2% zinc cut-off grade, this gives a total metal value
that is potentially economic for open-pit mining. The MRE incorporates the reasonable prospects for
eventual economic extraction assumed for open-pit mining.
The Inferred MRE for the Halls Peak deposit is reported using a cut-off grade of 2.0% zinc and is
shown in Table 8.
JORC
Classification
Inferred
Total
Table 8 – Halls Peak MRE summary table
Zn cut-off
Tonnage
Pb
Cu
Zn (%)
grade (%)
(Mt)
(%) (%)
2.0
0.84
3.7
1.5 0.44
Ag
ppm
30
Au
SG
ppm (calc)
0.1
2.80
Inferred
30
0.1
0.84
3.7
1.5
0.44
Exploration Target
An Exploration Target has been defined and is summarised in Table 9. The Exploration Target
assumes a 2.0% Zn cut-off grade, where the upper tonnage limit is based on the existing total
mineralisation inventory and the lower limit is half this value.
The lower target has higher grades, based around existing resource grades, while the higher target
has lower grades based around the difference between the resource and inventory grades.
The Exploration Target is in addition to the current MRE and affirm the potential to double the
Resource with comparable grade.
Table 9 – Halls Peak Exploration Target at 2.0% Zn Cut-off Grade
Target
Mt
Zn %
Pb %
Cu %
Ag ppm
Au ppm
Lower
Upper
0.5
1.0
3.7
2.7
1.5
1.1
0.44
0.34
33
27
0.12
0.08
This announcement has been approved for release by the Board of Directors.
-endsFor further information please contact
Alex Cheeseman
Managing Director
E: info@criticalresources.com.au
P: +61 (8) 9389 4499
Page 8 of 25
ABOUT CRITICAL RESOURCES LIMITED
Critical Resources is advancing and developing critical metals projects for a decarbonised future. The Company holds
a suite of lithium prospects across Ontario, Canada, including Mavis Lake, Graphic Lake, Plaid and Whiteloon Lake.
The Company’s other projects include the Block 4 and Block 5 copper project, located in Oman, and the Halls Peak
Project in NSW, Australia, a high-quality base metals project with significant scale potential.
The Company’s primary objective is the rapid development of its flagship Mavis Lake Lithium Project. Mavis Lake is an
advanced exploration project with near-term development potential. The Company completed over 19,500m of
drilling in 2022 and has commenced another significant drilling program in 2023. The Company has also commenced
initial studies that will underpin the transition from explorer to developer.
COMPETENT PERSONS STATEMENT
The information in this ASX Announcement that relates to Exploration Results is based on information compiled by
Mr Michael Leu, a Competent Person who is a member of the Australian Institute of Geoscientists (AIG) and the
Australian Institute of Mining and Metallurgy (AusIMM) and a consultant of Critical Resources. Mr Leu has sufficient
experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity
being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Leu consents to the inclusion in this
Announcement of the matters based on his information in the form and context in which it appears.
The information in this ASX Announcement that relates to Mineral Resource Estimate is based on information compiled
by and fairly represents Mr Arnold van der Heyden a Competent Person and Chartered Professional (Geology) of the
AusIMM. Mr van der Heyden is a full-time employee of H&S Consultants Pty Ltd. Mr van der Heyden has sufficient
experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity
being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr van der Heyden consents to the inclusion in
this Announcement of the matters based on his information in the form and context in which it appears.
FORWARD LOOKING STATEMENTS
This announcement may contain certain forward-looking statements and projections. Such forward-looking
statements/projections are estimates for discussion purposes only and should not be relied upon. Forward-looking
statements/projections are inherently uncertain and may therefore differ materially from results ultimately achieved.
Critical Resources Limited does not make any representations and provides no warranties concerning the accuracy of
the projections and disclaims any obligation to update or revise any forward-looking statements/projects based on new
information, future events or otherwise except to the extent required by applicable laws. While the information
contained in this report has been prepared in good faith, neither Critical Resources Limited or any of its directors, officers,
agents, employees or advisors give any representation or warranty, express or implied, as to the fairness, accuracy,
completeness or correctness of the information, opinions and conclusions contained in this announcement.
Page 9 of 25
Appendix 1 – Halls Peak Mineral Resource Estimate JORC 2012 Table 1
Section 1: Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections)
Criteria
JORC-Code Explanation
Commentary
Sampling
techniques
Nature and quality of sampling Allstate Exploration Diamond Drilling, 1969-1970
• Core stored by the Geological Survey of N.S.W. at WB
(e.g., cut channels, random
Clarke Geoscience Centre Londonderry Core Library
chips, or specific specialised
was
re-sampled.
industry standard measurement
• 1,120metres from 14 drill holes.
tools appropriate to the
minerals under investigation,
• Complete core and half core were halved using a
such as down hole gamma
diamond saw, with a half core from complete core and
sondes, or handheld XRF
quarter core from half core sent for assay and
instruments, etc). These
remainder core retained.
examples should not be taken
Precious Metal Resources Limited diamond drilling, 2014
as limiting the broad meaning
• 382metres from 5 holes
of sampling.
• Oriented HQ core was cut in half using a diamond
saw, with a half core sent for assay and half core
retained.
Include reference to measures
taken to ensure sample
representivity and the
appropriate calibration of any
measurement tools or systems
used.
Sovereign Gold Limited diamond drilling, 2016
• 637metres from 6 holes
• Oriented HQ core was cut in half using a diamond
saw, with a half core sent for assay and half core
retained.
Critical Resources Limited diamond drilling, 2021- 2022
• 4,782metres from 22 holes
Aspects of the determination of • Diamond Core drilling, NQ size, was used to recover
mineralisation that are Material
core in a 3m length barrel. The core is placed in 1m core
to the Public Report. In cases
trays with the drillers' core blocks indicating depth
measurement, drilled length and core recovered. Core
where ‘industry standard’ work
trays are then marked up in 1 metre lengths based on
has been done this would be
the driller's blocks.
relatively simple (e.g., ‘reverse
•
Oriented core was placed on a V-rail and fitted
circulation drilling was used to
together;
a consistent cut-line was drawn along the
obtain 1 m samples from which
core to ensure cutting (halving) of representative
3 kg was pulverised to produce
samples.
a 30 g charge for fire assay’). In • Oriented core was cut in halves using a diamond saw;
other cases more explanation
one half of the core was sent for assay and the other half
retained.
may be required, such as
where there is coarse gold that • Core sample intervals were based on geological logging
and the occurrence of visible mineralisation.
has inherent sampling
•
High resolution scaled photographs were taken of the
problems. Unusual commodities
core
as a physical record for later analysis.
or mineralisation types (e.g.,
• No other measurement tools other than
submarine nodules) may
directional survey tools have been used in the
warrant disclosure of detailed
holes at this stage.
information.
Samples were dispatched to an accredited laboratory (ALS)
in Brisbane, Australia for sample preparation and analysis.
Page 10 of 25
Criteria
JORC-Code Explanation
Commentary
Drilling
techniques
Diamond drill core was recovered in all drilling campaigns,
Drill type (e.g., core, reverse
circulation, open-hole hammer, refer to above.
rotary air blast, auger, Bangka,
Critical Resources Limited diamond drilling, 2021- 2022 NQ2
sonic, etc) and details (e.g.,
diamond
double tube coring by Sandvik DE710 rig was used
core diameter, triple or
throughout
the program.
standard tube, depth of
diamond tails, face-sampling
bit or other type, whether core
is oriented and if so, by what
method, etc).
Drill sample
recovery
Method of recording and
Lithological logging, photography
assessing core and chip sample
recoveries and results assessed.
Core samples were measured with a standard tape within
the core trays. Length of core was then compared to the
interval drilled, and any core loss was attributed to individual
rock units based on the amount of fracturing, abrasion of
core contacts, and the conservative judgment of the core
logger.
Measures taken to maximise
Results of core loss are discussed below.
sample recovery and ensure
representative nature of the
Experienced driller contracted to carry out drilling.
samples.
In broken ground the driller produced NQ core from short
runs to maximise core recovery.
Core was washed before placing in the core trays.
Whether a relationship exists
between sample recovery and Core was assessed by eye before cutting to ensure
grade and whether sample
representative sampling.
bias may have occurred due to
preferential loss/gain of
fine/coarse material.
Logging
Whether core and chip
samples have been
geologically and
geotechnically logged to a
level of detail to support
appropriate Mineral Resource
estimation, mining studies and
metallurgical studies.
Whether logging is qualitative
or quantitative in nature. Core
(or costean, channel, etc)
photography.
Core samples were not geotechnically logged.
Core samples have been geologically logged to support
appropriate Mineral Resource estimation, mining studies and
metallurgical studies.
The core logging was qualitative in nature, recording
features such as lithology, structure, oxidation and
alteration and sulphide mineralisation. The orientation of
planar features such as bedding and cleavage was
determined and recorded where possible.
Page 11 of 25
Criteria
JORC-Code Explanation
Commentary
The total length and
percentage of the relevant
intersections logged.
All core was photographed
100% of the relevant intersections were logged.
Sub-sampling If core, whether cut or sawn
Oriented core was placed V-rail and a consistent cut-line
techniques and and whether quarter, half or all drawn along core to ensure cutting (halving) of
sample
core taken.
representative samples
preparation
If non-core, whether riffled,
tube sampled, rotary split, etc
and whether sampled wet or
dry.
Oriented HQ or NQ core was cut in half using a diamond saw,
with a half core sent for assay and half core retained.
For all sample types, the nature, Core sample intervals were based in logged mineralisation
quality and appropriateness of
the sample preparation
No duplicates or second half-sampling
technique.
Quality control procedures
adopted for all sub-sampling
stages to maximise
representivity of samples.
Measures taken to ensure that
the sampling is representative
of the in situ material collected,
including for instance results for
field duplicate/second-half
sampling.
Whether sample sizes are
appropriate to the grain size of
the material being sampled.
Assays methods appropriate for style of mineralisation: MEQuality of assay The nature, quality and
data and
appropriateness of the assaying MS61 0.25g sample for 48 Elements and Gold by method AuAA25 30g sample. Samples have been sent to accredited
laboratory tests and laboratory procedures
Australian Laboratory Services (ALS)
used and whether the
technique is considered partial
or total.
ALS conducted appropriate quality assurance according to
Australian Standards. ALS issued QC Certificates for each
batch of samples assayed. This included control procedures
For geophysical tools,
spectrometers, handheld XRF adopted viz: standards, blanks and duplicate assays.
instruments, etc, the
parameters used in determining Variations were within acceptable limits. Acceptable levels
the analysis including
of accuracy and precision were confirmed.
instrument make and model,
Page 12 of 25
Criteria
JORC-Code Explanation
Commentary
reading times, calibrations
factors applied and their
derivation, etc.
Nature of quality control
procedures adopted (e.g.,
standards, blanks, duplicates,
external laboratory checks)
and whether acceptable levels
of accuracy (i.e., lack of bias)
and precision have been
established.
Verification of
sampling and
assaying
The verification of significant
intersections by either
independent or alternative
company personnel.
The use of twinned holes.
No independent verification completed at this stage
Hole CRR21DD_01 was drilled to twin hole SG_03. It confirmed
the occurrence and tenor of the mineralisation encountered
in SG_03.
Documentation of primary
data, data entry procedures, Core measured, photographed and logged by geologists.
data verification, data storage Digitally recorded plus back-up records.
(physical and electronic)
protocols.
Assay data presented in this report
Discuss any adjustment to assay
data.
Location of
data points
Accuracy and quality of
The CRR hole collars were picked up by a registered surveyor
surveys used to locate drill holes at the completion of the drill program.
(collar and down-hole surveys),
trenches, mine workings and
Historical drill holes were located using old maps and/or tape
other locations used in Mineral
and compass surveys. The collar elevation of these holes was
Resource estimation.
derived by projecting them onto the current topographic
Specification of the grid system surface. The accuracy of the old hole collars is estimated to
used.
be within 1-5m.
Quality and adequacy of
topographic control.
MGA94 (Zone 56)
Topographic control based on Department of Lands digital
terrain model.
Data spacing Data spacing for reporting of
and distribution Exploration Results.
Not relevant to current drilling.
Whether the data spacing, and
Core sample intervals were based in logged mineralisation
distribution is sufficient to
and no sample composting applied. Reporting of final results
establish the degree of
includes many weighted average- composting of a